“Investor Energy” LLC, an affiliated company of “Summa” Group, “RAO ES of the East” OJSC, the Primorsky Region Administration, the Ussuriysky Urban District Administration and the Nakhodkinsky Urban District Administration signed a letter of intent on implementation of construction projects regarding Ussuriyskaya and Nakhodkinska thermal power stations.
According to the document, “Investor Energy” LLC plans to implement construction project regarding Ussuriyskaya and Nakhodkinskaya thermal power stations in the Primorsky Region. The power capacity of two stations will amount to 740 MW (370 MW each). It is planned that Ussuriyskaya TPS will use coal, while Nakhodkinskaya TPS will use gas. Thestationsarescheduledtobebuiltin 2012-2015.
Alexander Vinokurov, First Vice President of Summa Group, says: “Having conducted the analysis, we came to the conclusion that there is a lack of generating capacities in the region. We presented our suggestions to the Primorsky Region Administration, as well as to the Ussuriysky Urban District Administration and the Nakhodkinsky Urban District Administration. Implementation of these projects will provide the consumers of the region with reliable electrical and heating supply. Moreover, itwillimprovetheecologyoftheregion”.
Summa Group team has extensive experience in running projects in the energy sector. In particular, “GlobalElectroService” OJSC (an affiliated company of Summa Group) has an extensive experience in implementation of projects of similar type, including construction of Sochi Power Station under the programme “Olympic objects construction and development of Sochi as a mountain and climatic resort”.
Specialists of GlobalElectroService have also been involved in international energy projects. Our clients include “Inter RAO UES” OJSC, “Federal Grid Company UES” OJSC, “Transneft” OJSC”, emphasized Alexander Vinokurov.
Sergei Tolstoguzov, acting General Director of “RAO ES of the East” OJSC, notes that “the signed letter of intent strengthens common interest among energy specialists, city and regional authorities in relation to development of energy infrastructure”. “The future development of the entire Primorsk Region relies on the coordinated and smooth running of the energy sector. That is why these projects are of vital importance to meet the increasing needs of electrical and heating supply in the Primorsk Region”, says Sergei Tolstoguzov.
***
“RAO ES of the East” OJSC was established on July 01, 2008 as a result of the reorganization of RAO “UES of Russia” OJSC. Its core activity is the distribution of electrical and thermal energy in the Eastern Region of Russia. “RAO ES of the East” owns packages of shares in power companies of the Far East such as “DEK” OJSC, JSC “Yakutskenergo” OJSC, “Magadanenergo” OJSC, “Kamchatskenergo” OJSC, “Sakhalinenergo” OJSC. Besides, “RAO ES of the East” OJSC owns packages of shares in “Peredvizhnaya Energetika” OJSC and some non-core companies transferred to the Holding Company under the separation balance sheet. The installed capacity of power stations of the Far East energy companies being a part of “RAO ES of the East” amounts to 8,819.74 MW.
According to the document, “Investor Energy” LLC plans to implement construction project regarding Ussuriyskaya and Nakhodkinskaya thermal power stations in the Primorsky Region. The power capacity of two stations will amount to 740 MW (370 MW each). It is planned that Ussuriyskaya TPS will use coal, while Nakhodkinskaya TPS will use gas. Thestationsarescheduledtobebuiltin 2012-2015.
Alexander Vinokurov, First Vice President of Summa Group, says: “Having conducted the analysis, we came to the conclusion that there is a lack of generating capacities in the region. We presented our suggestions to the Primorsky Region Administration, as well as to the Ussuriysky Urban District Administration and the Nakhodkinsky Urban District Administration. Implementation of these projects will provide the consumers of the region with reliable electrical and heating supply. Moreover, itwillimprovetheecologyoftheregion”.
Summa Group team has extensive experience in running projects in the energy sector. In particular, “GlobalElectroService” OJSC (an affiliated company of Summa Group) has an extensive experience in implementation of projects of similar type, including construction of Sochi Power Station under the programme “Olympic objects construction and development of Sochi as a mountain and climatic resort”.
Specialists of GlobalElectroService have also been involved in international energy projects. Our clients include “Inter RAO UES” OJSC, “Federal Grid Company UES” OJSC, “Transneft” OJSC”, emphasized Alexander Vinokurov.
Sergei Tolstoguzov, acting General Director of “RAO ES of the East” OJSC, notes that “the signed letter of intent strengthens common interest among energy specialists, city and regional authorities in relation to development of energy infrastructure”. “The future development of the entire Primorsk Region relies on the coordinated and smooth running of the energy sector. That is why these projects are of vital importance to meet the increasing needs of electrical and heating supply in the Primorsk Region”, says Sergei Tolstoguzov.
***
“RAO ES of the East” OJSC was established on July 01, 2008 as a result of the reorganization of RAO “UES of Russia” OJSC. Its core activity is the distribution of electrical and thermal energy in the Eastern Region of Russia. “RAO ES of the East” owns packages of shares in power companies of the Far East such as “DEK” OJSC, JSC “Yakutskenergo” OJSC, “Magadanenergo” OJSC, “Kamchatskenergo” OJSC, “Sakhalinenergo” OJSC. Besides, “RAO ES of the East” OJSC owns packages of shares in “Peredvizhnaya Energetika” OJSC and some non-core companies transferred to the Holding Company under the separation balance sheet. The installed capacity of power stations of the Far East energy companies being a part of “RAO ES of the East” amounts to 8,819.74 MW.